Renovations do not go wrong because somebody plastered badly. They go wrong because something was done earlier than it should have been, or later than it could have been. This article sets out the sequence and, for each stage, what is hard to change afterwards.

A house under renovation with steel partition framing and exposed structure

Why the order matters more than speed

Each stage of a renovation creates the conditions for the next. How true the walls are decides how tiling sits. Where the partitions stand decides where services run. The floor level decides whether the doors will close. Skipping a stage or doing it out of order causes nothing dramatic at the time, but putting it right later usually costs more than the original stage did.

The second reason is dust and water. Wet processes come before clean ones, because they are cleaned up after. Pouring screed onto a finished floor is a mistake that cannot be solved except by taking the floor up.

Stage by stage

Demolition and strip-out

Partitions, tiling, door frames and floors come out. Only now does the real state of the masonry and the services show. Hard to undo: a load-bearing wall. If you are not sure what carries load, this calls for a structural engineer and the procedure under Building Act 283/2021 Coll., not a hammer.

Brickwork and new partitions

The new layout goes up, lintels are set, openings are bricked up. Hard to undo: room widths and door positions. Moving a finished masonry partition means demolition all over again.

Services and chases

Electrics, water, waste. Chases are cut, boxes are set. Hard to undo: the route of the services. After plastering, chasing is done into a finished wall and it shows.

Core plaster and screeds

Walls brought true, floor brought to level. Hard to undo: trueness and level. Both decide the tiling, the kitchen and whether the doors will close.

Stucco and smooth surfaces

Finishing ready for paint. Hard to undo: smoothness under raking light. It can be re-skimmed, but that means more sanding and more dust in a finished flat.

Tiling and floors

Laid to finished levels. Hard to undo: the tile layout and the floor level at the doorway. Once bonded, only demolition changes it.

Paint, trims and finishing

The last layer. Hard to undo: nothing major, which is exactly why nothing that belonged earlier should be hidden here.

Where the order breaks down most often

  • A floor laid before plastering, because "we will cover it with sheeting".
  • Deciding on a television fixing after the drywall partition is closed up.
  • Tiling a bathroom before the services behind the service wall are finished.
  • Painting before making good after the electrician.
  • Planning a schedule without the curing breaks, which cannot be shortened.

Which of this a bricklayer does and to what extent is described on Demolition and brickwork, Drywall and partitions and Plaster and stucco.

More articles

Send your job description

Describe the job

No drawings or exact square metres needed. Write what should be done, what condition it is in now and when you would like it finished. We will ask about the rest.

  • We pass the enquiry to a firm that does masonry work in your area.
  • If we have no partner in your area, we say so straight away instead of leaving you waiting.
  • Photos of the current state help the most. You can send them to info@najdi-zednika.cz.

775 654 443
info@najdi-zednika.cz